You will be creating a work breakout structure, for a kitchen renovation project. It must be on Ms excel sheet. I will attach an example to follow bellow.
WBS Number Level 0 Level 1 Level 2 Level 3
1 Isley’s Recording Studio
1.1 General Administration
1.1.1 Permits
1.1.1.1 Obtain Business License
1.1.1.2 Obtain Building Permits
1.1.2 Building Architecture
1.1.2.1 Interview Architectual Firms
1.1.2.2 Hire Architectual Firm
1.1.2.3 Receive draft design
1.1.2.4 Review draft design
1.1.2.5 Review final design
1.1.2.6 Building design is complete
1.1.3 General Contractor
1.1.3.1 Submit RFP for Bidding
1.1.3.2 Receive Final Proposals
1.1.3.3 Score Proposals
1.1.3.4 Hire the GC Firm
1.1.3.5 GC Confirms and hires sub-contractors
1.2 Equipment
1.2.1 Audio Board with S/W
1.2.1.1 Research Audio Boards
1.2.1.2 Test Audio Board
1.2.1.3 Decide and purchase Audio Board
1.2.2 Mic’s and Mic stands
1.2.2.1 Research Mic’s and stands
1.2.2.2 Test Mic’s
1.2.2.3 Decide and purchase Mic’s and mike stands
1.2.3 Recording devices
1.2.3.1 Research Recording Devices
1.2.3.2 Test Recording Devices
1.2.3.3 Decide and purchase recording devices
1.2.4 Funiture
1.2.4.1 Purchase cabinetry for audio board and recording devices
1.2.4.2 Purchase Chairs and Couches
1.3 Construction
1.3.1 Electrical
1.3.1.1 Run all electrical wiring
1.3.1.2 Install light switches, wall sockets
1.3.1.3 Test all outlets
1.3.1.4 Inspect to confirm electrical meets code
1.3.1.5 Electrical approved
1.3.2 Plumbing
1.3.2.1 Run all water piping
1.3.2.2 Install Showers, Sinks, Toilets.
1.3.2.3 Test for leaks
1.3.2.4 Inspect to confirm plumbing meets code
1.3.2.5 Plumbing approved
1.3.3 Dry Walling
1.3.3.1 Install Dry Wall
1.3.3.2 Sand and apply second application of dry wall compound
1.3.3.3 Sand and wash walls
1.3.3.4 Conduct final inspection of dry wall installation
1.3.3.5 Dry Walling Approved
1.3.4 Flooring
1.3.4.1 Prepare floors for installation
1.3.4.2 Install flooring
1.3.4.3 Conduct final inspection of flooring installation
1.3.4.4 Flooring approved
1.3.5 Painting
1.3.5.1 Prepare walls and base boards for painting
1.3.5.2 Apply primer paint
1.3.5.3 Apply 2 coats of eggshell latex paint
1.3.5.4 Conduct final inspection of painting
1.3.5.5 Painting approved
1.4 Funiture and Equipment Installation
1.4.1 Funiture
1.4.1.1 Install all cabinetry in both studios
1.4.1.2 Run wiring to both studios
1.4.1.3 Apply sound proofing to recording chambers
1.4.2 Audio boards, recording devices and mic’s
1.4.2.1 Install and connect all audio equipment
1.4.2.2 Test all funtionality
1.4.2.3 Conduct final inspection of the studio
1.4.2.4 Studio is ready for operation
1.5 Project Closeout
1.5.1 Confirm GC has paid all subcontractors
1.5.2 Confirm all necessary paperwork is filed with the city and state
1.5.3 Conduct lessons learned sessions with the team
1.5.4 Throw a party like it’s 1999!!!
1.5.5 PROJECT COMPLETE!!
Instructions
For this assignment, you will create a Work Breakout Structure (WBS) for your project using Microsoft Excel. As an industry best practice, many project managers will build their WBS using MS Excel to provide a more simplistic view and analysis of the project’s work categories and the “Work Packages.” Once the WBS is approved, the project manager will import the data into the preferred corporate PM Tool. Examples of industry-leading tools include MS Project, Primavera, Clarity, TeamGantt, Monday.com, etc. you are ONLY required to submit your WBS in MS Excel.
Why Choose Us
- 100% non-plagiarized Papers
- 24/7 /365 Service Available
- Affordable Prices
- Any Paper, Urgency, and Subject
- Will complete your papers in 6 hours
- On-time Delivery
- Money-back and Privacy guarantees
- Unlimited Amendments upon request
- Satisfaction guarantee
How it Works
- Click on the “Place Order” tab at the top menu or “Order Now” icon at the bottom and a new page will appear with an order form to be filled.
- Fill in your paper’s requirements in the "PAPER DETAILS" section.
- Fill in your paper’s academic level, deadline, and the required number of pages from the drop-down menus.
- Click “CREATE ACCOUNT & SIGN IN” to enter your registration details and get an account with us for record-keeping and then, click on “PROCEED TO CHECKOUT” at the bottom of the page.
- From there, the payment sections will show, follow the guided payment process and your order will be available for our writing team to work on it.